PRINCE2 Foundation Exam is a multiple-choice exam that consists of 60 questions. PRINCE2Foundation exam is closed book, which means that candidates are not allowed to bring any study materials or notes into the exam room. PRINCE2Foundation exam is computer-based and can be taken at an accredited training center or online. PRINCE2Foundation exam lasts for one hour and candidates must achieve a score of at least 55% to pass. Successful candidates will receive a PRINCE2 Foundation certificate, which is a globally recognized qualification in project management.
PRINCE2 Foundation certification exam is suitable for individuals who are new to project management, as well as those who are experienced project managers. PRINCE2 7 Foundation written Exam certification is also beneficial for those who want to work in an organization that uses PRINCE2 methodology. PRINCE2 7 Foundation written Exam certification provides individuals with the knowledge and skills required to manage projects effectively, and it helps them demonstrate their proficiency in PRINCE2 methodology.
NEW QUESTION # 107
Which is part of quality control?
- A. Document the project's acceptance criteria in the Project Product Description
- B. Produce quality records to show that the planned quality activities have been carried out
- C. Define the quality responsibilities of those involved in the production of the products
- D. Maintain the corporate organization's quality management system
Answer: B
Explanation:
Producing quality records is a key part of quality control in PRINCE2. These records provide documented evidence that quality activities have been planned and executed according to the project's quality requirements, helping to ensure transparency and accountability in the quality management process.
References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.
NEW QUESTION # 108
Which is an objective of the Initiating a Project process?
- A. Prepare the plans for the subsequent stages
- B. Request authority from corporate management to deliver the project
- C. Develop the corporate quality management system as part of the Project Initiation Documentation
- D. Summarize how the organization's project management method will be tailored for the project
Answer: D
NEW QUESTION # 109
Why does the project board review the PID during an end stage assessment?
- A. To confirm that project controls are adequate for the remainder of the project
- B. To review summarized progress to date and decide what to do next with the project
- C. To notify the commissioning organization that the project has been authorized
- D. To ensure that post-project reviews of operational performance are planned
Answer: B
Explanation:
The project board reviews the Project Initiation Documentation (PID) during an end stage assessment primarily to review summarized progress to date and to decide the future course of action for the project. This review helps determine whether the project is still viable and if the project should continue into its next stage based on performance against the plan and the business case.References: PRINCE2 Foundation Manual
NEW QUESTION # 110
Which is part of quality control?
- A. Document the project's acceptance criteria in the Project Product Description
- B. Produce quality records to show that the planned quality activities have been carried out
- C. Define the quality responsibilities of those involved in the production of the products
- D. Maintain the corporate organization's quality management system
Answer: B
NEW QUESTION # 111
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A. Stage Plan
- B. Team Plan
- C. Product Description
- D. Work Package
Answer: D
NEW QUESTION # 112
Which is a true statement about time-driven controls?
- A. Time-driven controls take place when specific events happen
- B. An Exception Report is a time-driven control
- C. Time-driven controls are produced at the end of a stage
- D. Time-driven controls are used for monitoring the progress of Work Packages and management stages
Answer: D
Explanation:
Section: Volume B
NEW QUESTION # 113
What is a purpose of a Benefits Review Plan?
- A. Give a detailed analysis of only those benefits that were realized before the project closed
- B. Provide information regarding unfinished work to the group which will support the project's products in their operational life
- C. Document the justification for undertaking the project, based on the estimated costs versus the anticipated benefits
- D. Provide details of the time and effort needed to carry out the planned benefits reviews
Answer: D
NEW QUESTION # 114
Which theme estimates the cost of delivering the project?
- A. Business case
- B. PROGEESS
- C. Plans
- D. Change
Answer: A
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case
NEW QUESTION # 115
Which is a minimum requirement for applying the risk theme?
- A. Threats must be assessed for their impact on the viability of the project
- B. A single role that is responsible for all risks must be defined
- C. Team managers must maintain their own risk registers
- D. The PRINCE2 risk management procedure must be followed
Answer: A
Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-2017-risk-theme-changes/
NEW QUESTION # 116
Which process monitors work that has been assigned to a team manager?
- A. Controlling a stage
- B. Managing product delivery
- C. Managing a stage boundary
- D. Directing a project
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-process-managing-product-delivery.php
NEW QUESTION # 117
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
- A. End Stage Report
- B. Work Package
- C. Team Plan
- D. Project Plan
Answer: D
NEW QUESTION # 118
Which is an objective of the 'directing a project' process?
- A. To design the project management team roles
- B. To give authority to deliver the project product
- C. To select and appoint the project manager
- D. To create the plan to deliver the project product
Answer: B
Explanation:
An objective of the 'Directing a Project' process in PRINCE2 is to give authority to deliver the project product. This process is where the project board makes key decisions and exercises overall control while delegating day-to-day management of the project stages to the project manager.References: PRINCE2 Foundation Manual
NEW QUESTION # 119
Which is a purpose of the quality theme?
- A. To establish baselines against which any changes to products can be assessed
- B. To establish how the project will ensure that all products created meet their requirements
- C. To determine the communication needs of the organization's quality assurance function
- D. To identify all the products of the project to ensure the scope has been adequately defined
Answer: B
Explanation:
Section: Volume B
NEW QUESTION # 120
What is a risk actionee responsible for?
- A. Managing, monitoring and controlling of all aspects of an assigned risk
- B. Identifying risks to the project that might occur in their department
- C. Carrying out a risk response action to respond to a particular risk
- D. Owning and authorizing the use of the risk budget to fund risk responses
Answer: A
Explanation:
A risk actionee in PRINCE2 is responsible for managing, monitoring, and controlling all aspects of a specifically assigned risk. This role includes planning and implementing appropriate risk responses and ensuring that the risk is handled effectively throughout its lifecycle in the project.References: PRINCE2 Foundation Manual
NEW QUESTION # 121
Which is a purpose of the business case theme?
- A. To establish the controls to manage changes that may impact the project benefits
- B. To establish a viable investment proposition
- C. To identify the project's outputs
- D. To identify which role is responsible for producing the business case
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Business_Case
NEW QUESTION # 122
What may be funded from a risk budget?
- A. Preparation of the risk management approach
- B. Implementation of a fallback plan
- C. Corrections required due to off-specifications
- D. Impact analysis of requests for change
Answer: B
Explanation:
Reference http://prince2.wiki/Risk#Risk_Budget
NEW QUESTION # 123
Which describes a risk event?
- A. The derivation or sources of a potential risk to the project
- B. The area of uncertainty in terms of the threat or opportunity
- C. The sequence of events and actions that will be put in place if a risk occurs
- D. The achievement of a milestone on the project plan
Answer: B
Explanation:
Reference http://prince2.wiki/Risk
NEW QUESTION # 124
Which statement applies to Stage Plans?
- A. Are produced at the same time as the Project Initiation Documentation
- B. Always have the same duration as the Project Plan
- C. Assist the Project Manager in the day-to-day running and control of the project
- D. Provide a baseline against which the Project Board monitor overall progress
Answer: C
NEW QUESTION # 125
Which is a minimum requirement for applying the change theme?
- A. To establish a change budget to fund changes in scope
- B. To record every issue that is raised in the issue register
- C. To appoint the project manager as part of the change authority
- D. To define the project's approach to baselining products
Answer: B
Explanation:
Reference http://prince2.wiki/Themes#Change_Theme
NEW QUESTION # 126
Which describes a management activity within a project?
- A. Encouraging a project team to continue working on a particularly challenging product
- B. Seeking feedback from team members to ensure they are still aligned to the project's objectives
- C. Discussing project objectives with key stakeholders during a requirements gathering workshop
- D. Agreeing a work package with a team manager to deliver products within agreed tolerances
Answer: D
Explanation:
In PRINCE2, a management activity within a project typically involves formal agreements and organizational actions. Agreeing on a work package with a team manager is a core management activity, where specific tasks, responsibilities, and tolerances are defined and communicated, ensuring that the project's delivery aligns with the planned objectives and constraints.References: PRINCE2 7 Foundation study materials on project management activities.
NEW QUESTION # 127
Which is a purpose of the Starting up a Project process?
- A. Define the means of communication between the project and corporate or programme management
- B. Define the project controls
- C. Record any identified risks in the Risk Register
- D. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION # 128
Which describes an off-specification?
- A. A prototype demonstrating a possible design solution
- B. The addition of an improvement to a product description
- C. The production of more than the defined quantity of a specialist product
- D. An interdependency between products that was previously unidentified
Answer: C
Explanation:
An off-specification in PRINCE2 is a situation where a planned product does not meet its quality criteria or other requirements specified in the product description. This could include producing more or less than the defined quantity, implying deviation from the agreed specifications. References: PRINCE2 Foundation Handbook, Off-Specifications section.
NEW QUESTION # 129
......