AACE International AACE-PSP (Planning and Scheduling Professional) Certification is a highly-respected credential for project planning and scheduling professionals. With its globally-recognized reputation, the certification offers numerous career opportunities and advancement prospects to those who hold it. Planning & Scheduling Professional (PSP) Exam certification has become increasingly essential in today’s competitive business environment, where organizations seek professionals who can manage complex projects and bring them to successful completion. The AACE-PSP certification program offers an exceptional opportunity for individuals to showcase their skills and gain recognition as valued professionals in the field of cost engineering and project management.

 

NEW QUESTION # 42
What is the actual duration as of the status date or data date of Activity B?

  • A. 4.
  • B. 3.
  • C. 0.
  • D. 7.

Answer: B


NEW QUESTION # 43
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  • A. Production output.
  • B. Acceleration.
  • C. Productivity efficiency.
  • D. Productivity loss.

Answer: D


NEW QUESTION # 44
The linear scheduling velocity diagram has the following two-axis:

  • A. Location and crew size
  • B. Time and rate of progress
  • C. Time and location
  • D. Time and crew size

Answer: B


NEW QUESTION # 45
Determine the correct formula and date for the late start for Activity 9001.

  • A. LS.6001 Dur.6001 -> 11-20-02.
  • B. There is insufficient data provided to calculate the answer.
  • C. LF.9001 Dur.9001 -> 11-20-02.
  • D. The early finish is required in order to determine the answer.

Answer: C


NEW QUESTION # 46
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

  • A. 1001, 2002, 2002, 2003, 3001
  • B. 2001, 2002, 2003, 2007
  • C. 1001, 2002, 2003
  • D. 1001, 2001, 2002, 2003

Answer: D


NEW QUESTION # 47
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Installation phase.
  • B. Planning and design phase.
  • C. Turnover and start-up phase.
  • D. Claims and disputes phase.

Answer: B


NEW QUESTION # 48
How many work days does it take to move the product from testing to sale?

  • A. 100.
  • B. 90.
  • C. 70.
  • D. 60.

Answer: A


NEW QUESTION # 49
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the progressed portion of the critical path of all the updates previous to the current update.
  • B. Use the progressed portion of the critical path of the baseline schedule.
  • C. Use the forward-looking critical path of the most current updates.
  • D. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

Answer: C


NEW QUESTION # 50
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. Yes, by 14 calendar days.
  • B. Yes, by 4 calendar days.
  • C. NO.
  • D. Yes, by 9 calendar days.

Answer: B


NEW QUESTION # 51
What is the relationship depicted between Activity G and Activity H?

  • A. You cannot tell with the supplied information.
  • B. Finish-to-start.
  • C. Start-to-start.
  • D. Finish-to-finish.

Answer: C


NEW QUESTION # 52
Why does activity 11001 not show successor activities?

  • A. It is the final activity for the required work for the project
  • B. It is the penultimate work required for the project
  • C. The scheduler forgot to add the successor activities
  • D. The early finish and late finish are circular

Answer: A


NEW QUESTION # 53
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-04-02.
  • B. 06-18-02.
  • C. 06-11-02.
  • D. 06-05-02.

Answer: D


NEW QUESTION # 54
How much Total Float does drafting the product manual have?

  • A. 5 workdays.
  • B. 0 workdays.
  • C. 10 workdays.
  • D. 15 workdays.

Answer: C


NEW QUESTION # 55
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

  • A. 09-08-01.
  • B. 09-28-01.
  • C. 09-18-01.
  • D. 09-15-01.

Answer: A


NEW QUESTION # 56
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 15 days.
  • B. 5 days.
  • C. 0 days.
  • D. 10 days.

Answer: B


NEW QUESTION # 57
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. ADM uses arrows, while PDM uses boxes.
  • B. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • C. ADM is manual CPM calculations, while PDM is computerized.
  • D. ADM is limited to finish-to-start logic relationships, while PDM is not.

Answer: D


NEW QUESTION # 58
What was the original planned duration for Activity A through Activity G?

  • A. 28.
  • B. 24.
  • C. 25.
  • D. 26.

Answer: A


NEW QUESTION # 59
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. B.
  • B. C.
  • C. S.
  • D. W.

Answer: C


NEW QUESTION # 60
Activity C is a

  • A. Continuous activity.
  • B. Milestone.
  • C. Contentious activity.
  • D. 1-day activity.

Answer: B


NEW QUESTION # 61
Which of the following is NOT input data to the construction planning process?

  • A. The contract
  • B. Bonding capacity of subcontractors
  • C. Input from the owner
  • D. Input from the contractor

Answer: B


NEW QUESTION # 62
A driving relationship is _____________________.

  • A. A finish-to-start relationship.
  • B. The link between two related activities.
  • C. The link between a predecessor and the activity whose dates it controls.
  • D. A critical relationship.

Answer: C


NEW QUESTION # 63
What is the result of a forward pass calculation?

  • A. Value of free float for individual activities
  • B. Critical path
  • C. Value of total float for individual activities
  • D. Early start and early finish date for individual activities

Answer: D


NEW QUESTION # 64
What does the heavy, vertical line at "X" represent?

  • A. The status or data date.
  • B. International Date Line.
  • C. Change-over limits.
  • D. Delay fault line.

Answer: A


NEW QUESTION # 65
......


The AACE-PSP certification is highly respected in the project management industry and is recognized as a mark of excellence in project scheduling and planning. Planning & Scheduling Professional (PSP) Exam certification provides individuals with the necessary skills and knowledge to effectively manage project schedules and budgets, and to ensure that projects are completed on time and within budget. With the AACE-PSP certification, professionals can enhance their career opportunities and increase their earning potential.

 