
[Aug-2026] Verified SAP Exam Dumps with E-ACTAI-2601 Exam Study Guide
Best Quality SAP E-ACTAI-2601 Exam Questions DumpsFree Realistic Practice Exams [2026]
NEW QUESTION # 25
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
- A. Durations of all sprints for the full release defined based on planned complexity.
- B. User Stories are in Ready state for only the first 2 to 3 sprints.
- C. Project scope and planning are completed and final.
- D. Scope and duration of testing is finalized.
Answer: B
NEW QUESTION # 26
Which of the following are included in ready-to-use content in SAP Activate? Note: There are 2 correct answers to this question.
- A. SAP Best Practices
- B. Baseline Activation Service
- C. Business models from leading companies in each industry sector
- D. Project accelerators
Answer: A,D
NEW QUESTION # 27
What solution operations framework can customers use to create a joint business and IT organization?
- A. Transformation Management Office
- B. Customer Center of Expertise
- C. SAP Roadmap Explorer
- D. Solution Standardization Board
Answer: C
NEW QUESTION # 28
What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 2 correct answers to this question.
- A. Process benchmarking expertise
- B. Technology and architecture expertise
- C. Business process expertise
- D. Project management expertise
Answer: B,D
NEW QUESTION # 29
What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct answers to this question.
- A. Set variable sprint duration based on work.
- B. Adjust sprint duration based on team availability.
- C. Establish fixed duration of each sprint.
- D. Sprint duration between 1 week to 4 weeks.
Answer: A,B
NEW QUESTION # 30
What is the purpose of the scrum board? Note: There are 2 correct answers to this question.
- A. To represent the work
- B. To visualize scrum team progress
- C. To represent the scrum team setup
- D. To manage the scrum resources load
Answer: B
NEW QUESTION # 31
What information does the Scrum team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.
- A. Anchor user story in the backlog
- B. Number of backlog user stories
- C. Definition of Done
- D. Definition of Ready
Answer: C,D
NEW QUESTION # 32
Which of the following are benefits of using ready-to-use content? Note: There are 2 correct answers to this question.
- A. Fast time-to-value
- B. Maximized total cost of ownership
- C. Predictable results
- D. Exhaustive solution documentation
Answer: A,C
NEW QUESTION # 33
Where do you activate SAP Best Practices from Cloud ALM to be used during the fit-to-standard workshops for SAP S/4HANA Cloud Public Edition?
- A. Development System
- B. Production System
- C. Starter System
- D. Quality System
Answer: C
NEW QUESTION # 34
Which applications include content for integration scenarios? Note: There are 2 correct answers to this question.
- A. SAP Signavio Process Navigator
- B. SAP Cloud Appliance Library
- C. SAP Business Accelerator Hub
- D. SAP Solution Manager
Answer: A,C
NEW QUESTION # 35
Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?
- A. Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days
- B. Leveraging effort estimates for similar User Stories from another Scrum team
- C. Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team
- D. Detailed bottom-up estimates that break each User Story into shorter tasks
Answer: C
NEW QUESTION # 36
In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data?
- A. Product backlog
- B. Burndown chart
- C. Release plan
- D. Scrum board
Answer: B
NEW QUESTION # 37
In which phase do you create "an ordered list of everything that is known to be needed in the product"?
- A. Prepare
- B. Realize
- C. Discover
- D. Explore
Answer: D
NEW QUESTION # 38
Which techniques should the SAP Activate practitioner follow? Note: There are 3 correct answers to this question.
- A. Reduce business user involvement for efficiency
- B. Leverage dynamic extensibility and integrations
- C. Use agile approach throughout the project
- D. Apply the fit-to-standard first mindset
- E. Optimize testing by running it only at the end of Realize phase
Answer: B,C,D
NEW QUESTION # 39
Which of the following belong to the Application Design and Configuration workstream in the Explore phase? Note: There are 2 correct answers to this question.
- A. Change Impact Analysis
- B. Fit-to-standard workshop
- C. Configuration definition
- D. Integration prerequisites confirmation
Answer: B,C
NEW QUESTION # 40
In which phase of SAP Activate does the SAP Project Manager set up project governance?
- A. Prepare
- B. Realize
- C. Discover
- D. Explore
Answer: A
NEW QUESTION # 41
......
Authentic Best resources for E-ACTAI-2601: https://prep4sure.dumpsfree.com/E-ACTAI-2601-valid-exam.html